Performance Measures

Comparison Of Actual And Budget Expense 

The Goal Of The District Is To Not Exceed The Annual Approved Budget

Graph of 2025 expenses: Budget is stable; actual expenses drop until May, spike in June, then fall sharply in July.

Designation Of Reserves 

The Goal Of The District Is To Maintain A Four Month Operating Reserve 100% Of The Time

Bar chart titled "Designation of Reserves" shows monthly goal (blue) and actual (red) bars at 100% from January to December.

Claims By Customers 

The Goal Of The District Is To Have No More Than Three Claims Per Year

Bar chart titled "Claims by Customers" showing goal of 3 claims; actual claims not shown.

Customer Complaints 

The Goal Of The District Is For Customer Complaints Not To Exceed .1% Of Our Approximately 7,400 Customers

Graph of customer complaints: actual complaints decrease from 4 in January to 1-2 by July; goal is constant at 8 complaints per month.

Loss Work Time (worker's Compensation) 

The Goal Of The District Is To Experience Loss Work Time Of No More Than 8 Hours Per Month/96 Hours Per Year, About .002% Of The Hours Worked

Bar chart titled "Annual Loss Work Time" showing no actual hours and around 100 goal hours.

Employee Turnover 

The Goal Of The District Is To Retain Staff And Minimize Turnover To One Position (4% Of Staffing) Per Year

Bar chart showing annual employee turnover: Actual (3), Goal (1).

Maintenance Management 

The Goal Of The District Is Not To Exceed More Than 5% Backlogged Work Orders Per Month

Maintenance chart showing 5% goal, actual close to 0% from Jan to Aug.

 

Water Quality 

The Goal Of The District Is 100% Compliance For Water Quality

Bar chart of water quality compliance, showing "Goal" and "Actual" percentages from January to December.

Disruption Of Service 

The Goal Of The District Is To Complete Repairs Disrupting Water Service In Under 5 Hours

Graph showing monthly water service disruptions: goal at 4 hours, infrastructure disruptions vary, peak at June/August, low in April/July.

NPDES Requirements

The Goal Of The District Is To Meet 100% Of The Permit Limits 100% Of The Time

Bar chart of regulatory compliance for months Jan-Dec, comparing goal (blue) to actual (red).

Maintain Sewer System 

The Goal Of The District Is To Clean And/or Video The Entire Collections System Every 3 Years Or Less (the National Standard Is 3 To 5 Years)

Line graph of sewer line cleaning footage by month; actual vs. goal. Actual exceeds goal from January to August.

Overall Wastewater System Maintenance 

The Goal Of The District Is Not To Exceed More Than 5% Backlogged Work Orders Per Month

Line chart of backlogged work orders, 2023. Goal: 5% monthly. Actual starts at 0.8% in Jan, drops to near 0% by Mar, stays low all year.